CN110979105B CN201911348665.0A CN201911348665A CN110979105B CN 110979105 B CN110979105 B CN 110979105B CN 201911348665 A CN201911348665 A CN 201911348665A CN 110979105 B CN110979105 B CN 110979105B
Authority
CN
China
Prior art keywords
power supply
traction
external power
node
supply system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201911348665.0A
Other languages
Chinese (zh)
Other versions
CN110979105A (en
Inventor
智慧
邓云川
林宗良
李剑
袁勇
宋梦容
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201911348665.0A priority Critical patent/CN110979105B/en
Publication of CN110979105A publication Critical patent/CN110979105A/en
Application granted granted Critical
Publication of CN110979105B publication Critical patent/CN110979105B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B60VEHICLES IN GENERAL
    • B60MPOWER SUPPLY LINES, AND DEVICES ALONG RAILS, FOR ELECTRICALLY- PROPELLED VEHICLES
    • B60M3/00Feeding power to supply lines in contact with collector on vehicles; Arrangements for consuming regenerative power

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a method for designing an external power supply access scheme of a run-through bilateral traction power supply system in the field of planning of traction power supply systems of electrified railways, which comprises the following steps: s1, acquiring load process data of the through bilateral traction power supply system, acquiring a position information set input into a traction substation and an external power supply node position information set, and constructing an initial position information set; s2, establishing a target function which penetrates through an external power supply planning optimization model of the bilateral traction power supply system, and establishing constraint conditions of the optimization model; and S3, solving the optimization model according to the objective function and the constraint condition. The invention can effectively reduce the investment cost of the transmission network line between external power supplies, can effectively reduce the investment cost of the treatment project required by treating the unbalance of the three-phase voltage and voltage, and saves the investment cost for running through the running loss period of the bilateral traction power supply system.

Description

Design method for external power supply access scheme of through bilateral traction power supply system
Technical Field
The invention relates to the field of planning of traction power supply systems of electrified railways, in particular to a design method of an external power supply access scheme of a through bilateral traction power supply system.
Background
Due to the fact that partial areas of the electrified railway approach are not covered by a power grid or lack of powerful power supply support, the power supply of a single external power supply cannot meet the huge power requirements of high-speed motor train units and freight trains, and the voltage drop of a contact network is caused in severe cases, so that the driving safety is endangered. On the other hand, the electric phase separation arranged in the traction substation and the tail end subarea causes serious speed loss of the train, increases the energy consumption of the system, and can prevent the train from passing through the electric phase separation when the electric phase separation with the gradient of 30 per mill is passed. Therefore, a through bilateral traction power supply system needs to be constructed, and the advantages of the through bilateral traction power supply system are that at least half of the number of electric phase splitting is cancelled, the power supply capacity of the traction power supply system is greatly improved, the loss is reduced, and the win-win goal is achieved.
However, the key technical problem to be solved urgently by the through bilateral traction power supply system is how to solve the problem of current passing through a traction network and the problem of serious three-phase voltage unbalance. Therefore, the above-mentioned key technical problems should be solved at the same time when external power access scheme planning is developed.
Disclosure of Invention
The invention provides a design method of an external power supply access scheme of a through bilateral traction power supply system aiming at solving the problems in the prior art, and aims to obtain an external power supply access scheme meeting the power supply requirement, and effectively reduce the investment cost of a power transmission network circuit between external power supplies, the treatment project investment cost required by treating the three-phase voltage unbalance, the running loss of the through bilateral traction power supply system and the traction network through current.
In order to achieve the above purpose, the invention provides the following technical scheme:
a through bilateral traction power supply system external power supply access scheme design method comprises the following steps:
s1, acquiring load process data of the through bilateral traction power supply system, and acquiring a position information set input into a traction substation and an external power supply node position information set;
s2, establishing a target function of the external power supply planning optimization model of the run-through bilateral traction power supply system according to the load process data of the run-through bilateral traction power supply system, the position information collection input to the traction substation and the position information collection of the external power supply node, wherein the target function is as follows: the sum of the investment cost of the transmission network line, the investment of the three-phase voltage unbalance treatment project and the expected running loss value of the through bilateral traction power supply system is minimized;
establishing a constraint condition of an optimization model according to load process data of a through bilateral traction power supply system and a three-phase voltage unbalance limit value;
and S3, solving the objective function and the constraint condition to obtain an optimized external power access scheme of the through bilateral traction power supply system.
As a preferred embodiment of the present invention, the objective function is,
Figure GDA0003632163930000021
the subscript l represents the line number of an external power supply, g represents the number of a three-phase voltage unbalance treatment device of the traction substation, tt represents the number of a traction transformer of the traction substation, q represents the number of a traction network between two adjacent traction substations, and omegaLRepresents the newly-built line collection of the external power supply omegaGDevice for treating three-phase voltage unbalance of representative traction substationTRepresenting a collection of traction transformers, omega, of a traction substationQNRepresenting a traction network aggregation between two adjacent traction substations. c. ClFor the investment cost of newly-built line l, ulPut a decision variable, u, for line ll1 is investment line l, ul0 is a non-investment linegInvestment cost v of three-phase voltage unbalance treatment device g for newly-built traction substationgPutting into operation decision variable v of three-phase voltage unbalance treatment device ggThree-phase voltage unbalance treatment device g, v for investment constructiong0 is no investment to build three-phase voltageA balance treatment device g is arranged on the upper portion of the device,
Figure GDA0003632163930000031
in order to achieve active power loss during the operation of the line l,
Figure GDA0003632163930000032
the active power loss when a single-phase traction transformer tt of a traction substation operates,
Figure GDA0003632163930000033
in order to provide active power loss during operation of the traction network q,
Figure GDA0003632163930000034
representing expected value of running loss, sigma, of through bilateral traction power supply system1、σ2And σ3The weight coefficients are respectively the investment cost of the transmission network line, the investment of the three-phase voltage unbalance treatment project and the expected value of the running loss of the run-through bilateral traction power supply system.
As a preferable aspect of the present invention, the constraint conditions include: the method comprises the steps of node active power balance constraint, transmission capacity constraint of a transmission line, traction network through current constraint, traction substation three-phase voltage unbalance constraint and contact network working voltage fluctuation constraint.
As a preferred solution of the present invention, the formula of the node active power balance constraint is,
Figure GDA0003632163930000035
wherein p istsLoad active power, p, of traction substation ts for connection to external power i nodedIs the active power, omega, of other loads d on the external power supply inodeTS,iRepresenting a set of traction substations, Ω, located at the i-node of an external power supplyD,iRepresenting other sets of loads, Ω, at the external supply i-nodeL,iRepresents a power transmission line collection omega with a node i as a head end and a node j as a tail endL,jRepresenting a power transmission line collection with a node j as a head end and a node i as a tail end,pl,ijand pl,jiFor the active power transmitted on the transmission line l, the external power supply nodes at the head end and the tail end are respectively a node i and a node j, ij represents the node from the external power supply node i at the head end to the external power supply node j at the tail end, and ji represents the node from the external power supply node j at the tail end to the external power supply node i at the head end.
As a preferred aspect of the present invention, the transmission capacity constraint of the transmission line is formulated as,
Figure GDA0003632163930000036
wherein f islFor transmission capacity of transmission line, -fl min、fl maxRespectively the lower limit and the upper limit of the power flow of the transmission line l, ulPut a decision variable, Ω, for line lLAnd a new line set represents the external power supply, and the subscript l represents the line number of the external power supply.
As a preferred scheme of the invention, the transmission capacity constraint of the transmission line is converted into a mixed integer linear constraint expression which is easy to solve by a Big-M method:
-ulM1≤fl≤ulM2
wherein M is1And M2Is a positive number of ulAnd (5) putting decision variables for the line l.
As a preferred embodiment of the present invention, the traction network through-current constraint is formulated as,
Figure GDA0003632163930000041
wherein the subscripts x and x 'both represent a phase of the phase sequence a, b, c, satisfying x ≠ x',
Figure GDA0003632163930000042
and
Figure GDA0003632163930000043
are respectively flow-through tractionThe actual through-current and through-current allowed values of the lead net,
Figure GDA0003632163930000044
and
Figure GDA0003632163930000045
respectively representing two-phase current flowing into the single-phase traction transformer tt, epsilon being the ratio of the voltage at the high-voltage side of the single-phase traction transformer tt to the traction voltage, Zs,iEquivalent impedance, Z, at external power supply node i for traction substation ts accessttImpedance, Z, of single-phase traction transformer tt of traction transformerqTo the impedance of the traction network, Zl,tsiTo connect the line impedance between the traction substation ts and the external power supply node i.
As a preferred scheme of the invention, the three-phase voltage unbalance constraint of the traction substation is expressed by a formula,
Figure GDA0003632163930000046
wherein, the first and the second end of the pipe are connected with each other,
Figure GDA0003632163930000047
for negative-sequence currents, VUF, generated by traction substations ts*For three-phase voltage unbalance limits, UqFor drawing net pressure, SdcAnd epsilon is the ratio of the voltage of the high-voltage side of the single-phase traction transformer tt to the traction measurement voltage, which is the short-circuit capacity of the traction transformer.
As a preferred scheme of the invention, the fluctuation constraint of the working voltage of the overhead line system is expressed by a formula,
Figure GDA0003632163930000051
wherein the content of the first and second substances,
Figure GDA0003632163930000052
and
Figure GDA0003632163930000053
respectively the lowest voltage and the highest voltage, U, allowed by a contact network when the traction power supply system operates normallyqIs the working voltage of the contact net.
Based on the same conception, the invention also provides a through bilateral traction power supply system external power supply access scheme design system, which comprises at least one processor and a memory in communication connection with the at least one processor; the memory stores instructions executable by the at least one processor to enable the at least one processor to perform the method of any one of the above.
Compared with the prior art, the invention has the beneficial effects that:
(1) the invention provides an optimization model for external power supply planning of a through bilateral traction power supply system, so that the provided external power supply access scheme can effectively reduce the investment cost of a transmission network line between external power supplies, can effectively reduce the investment cost of treatment engineering required for treating three-phase voltage unbalance, and saves the investment cost for the running loss period of the through bilateral traction power supply system.
(2) According to the method, the mixed integer linear programming model is established, so that the optimization solver can be used for solving directly, and the complexity of solving the mixed integer nonlinear model is avoided.
Drawings
FIG. 1 is a flow chart of a method for designing an external power access scheme for a run-through bilateral traction power supply system according to the present invention;
fig. 2 is a schematic diagram of a through bilateral traction power supply system and an external power supply in embodiment 2 of the present invention;
fig. 3 is a schematic diagram of an external power supply scheme of a through bilateral traction power supply system optimized by the present invention in embodiment 2 of the present invention;
fig. 4 is a schematic diagram of an external power supply scheme of the single-side traction power supply system optimized by the present invention in embodiment 2 of the present invention.
Detailed Description
The present invention will be described in further detail with reference to test examples and specific embodiments. It should be understood that the scope of the above-described subject matter is not limited to the following examples, and any techniques implemented based on the disclosure of the present invention are within the scope of the present invention.
Example 1
The flow chart of the design method of the external power supply access scheme of the through bilateral traction power supply system is shown in figure 1, and the specific steps comprise:
step 1: and inputting parameters of railway lines, trains and schedules by using a professional traction load process simulation platform, such as ELBAS/WEBANET software or OpenPowerNet, and simulating to obtain load process data of the run-through bilateral traction power supply system. And inputting the position information collection of the traction substation and the external power supply node to obtain an initial position information collection.
And 2, step: the objective function for establishing an external power supply planning optimization model of the run-through bilateral traction power supply system is as follows: the objective function is to minimize the sum of the investment cost c of the transmission network line, the investment g of the three-phase voltage unbalance treatment project and the expected value F of the running loss of the through bilateral traction power supply system.
Figure GDA0003632163930000061
In the formula (1), subscript l represents a line number of an external power supply, g represents a three-phase voltage unbalance treatment device number of a traction substation, tt represents a traction transformer number of the traction substation, and t represents a traction network number between two adjacent traction substations. OmegaLRepresents the newly-built line collection of the external power supply omegaGDevice for treating three-phase voltage unbalance of representative traction substationTRepresenting a collection of traction transformers, omega, of a traction substationQNRepresenting the traction network collection between two adjacent traction substations. c. ClFor the investment cost of newly-built line l, ulPut a decision variable, u, for line ll1 is the investment to construct the line l, ul0 is a non-investment linegInvestment cost v of three-phase voltage unbalance treatment device g for newly-built traction substationgFor the unbalanced treatment of three-phase voltage dressPut-in decision variable of g, vgThree-phase voltage unbalance treatment device g, v for investment constructiongAnd 0 is a three-phase voltage unbalance treatment device g which is not invested in construction.
Figure GDA0003632163930000071
In order to achieve active power loss during the operation of the line l,
Figure GDA0003632163930000072
for the active power loss when a single-phase traction transformer tt of a traction substation operates,
Figure GDA0003632163930000073
in order to provide active power loss during operation of the traction network q,
Figure GDA0003632163930000074
and the expected value of the running loss of the through bilateral traction power supply system is shown. Sigma1、σ2And σ3The weight coefficients are respectively the investment cost of the transmission network line, the investment of the three-phase voltage unbalance treatment project and the expected value of the running loss of the run-through bilateral traction power supply system.
And step 3: and establishing constraint conditions of an optimization model according to the operating parameters of the external power supply and the run-through bilateral traction power supply system and the three-phase voltage unbalance limit value.
The method comprises node power balance constraint, transmission capacity constraint of a power transmission line, traction network through current constraint, traction substation three-phase voltage unbalance constraint and contact network working voltage constraint.
Node active power balance constraint:
Figure GDA0003632163930000075
in the formula (2), ptsLoad active power, p, of traction substation ts for connection to external power i nodedActive power of other loads d on an external power supply node i; the subscript ts represents the traction substation load connected to the external power i node, d represents the external powerOther loads on the power inode. OmegaTS,iRepresenting a set of traction substations, Ω, located at the i-node of an external power supplyD,iRepresenting other loads at the i node of the external power supply, omega Li representing the power transmission line set with the i node as the head end and the j node as the tail end, omegaL,jAnd representing a power transmission line collection taking the node j as a head end and the node i as a tail end. p is a radical ofl,ijAnd pl,jiFor the active power transmitted on the transmission line l, the external power supply nodes at the head end and the tail end are respectively a node i and a node j, ij represents the node from the external power supply node i at the head end to the external power supply node j at the tail end, and ji represents the node from the external power supply node j at the tail end to the external power supply node i at the head end.
Transmission capacity constraint of the transmission line:
Figure GDA0003632163930000081
in the formula (3), flFor transmission capacity of transmission line, -fl min、fl maxRespectively the lower limit and the upper limit of the power flow of the transmission line l, ulPut a decision variable, Ω, for line lLAnd a new line set represents the external power supply, and the subscript l represents the line number of the external power supply.
And (3) restraining the current passing through the traction network:
Figure GDA0003632163930000082
in the formula (4), subscripts x and x ' both represent a certain phase of the phase sequence a, b, c, but the values of the subscripts x and x ' cannot be consistent at the same time, namely x is not equal to x ',
Figure GDA0003632163930000083
and
Figure GDA0003632163930000084
respectively the actual through current and the allowable through current value flowing through the traction network,
Figure GDA0003632163930000085
and
Figure GDA0003632163930000086
respectively representing two-phase current flowing into the single-phase traction transformer tt, epsilon being the ratio of the voltage at the high-voltage side of the single-phase traction transformer tt to the traction voltage, Zs,iEquivalent impedance, Z, at external power supply node i for traction substation ts accessttImpedance, Z, of single-phase traction transformer tt of traction transformerqTo the impedance of the traction network, Zl,tsiTo connect the line impedance between the traction substation ts and the external power supply node i.
Three-phase voltage unbalance constraint of traction substation
Figure GDA0003632163930000087
In the formula (5), the first and second groups,
Figure GDA0003632163930000091
for negative-sequence currents, VUF, generated by traction substations ts*Is a three-phase voltage unbalance limit value, U, specified in the three-phase voltage unbalance (GB/T15543-qFor drawing net pressure, SdcAnd epsilon is the ratio of the voltage of the high-voltage side of the single-phase traction transformer tt to the traction measurement voltage, which is the short-circuit capacity of the traction transformer.
Constraint of working voltage fluctuation of contact network
Figure GDA0003632163930000092
In the formula (6), according to the design specification of railway electric traction power supply (TB 10009-2016),
Figure GDA0003632163930000093
and
Figure GDA0003632163930000094
respectively for traction power supply systemThe lowest voltage and the highest voltage allowed by the contact system in normal operation.
And 4, step 4: and (3) establishing an optimization model according to the objective function obtained in the step (2) and the constraint condition obtained in the step (3), further processing the mixed integer nonlinear constraint in the optimization model, and converting the mixed integer nonlinear constraint into a mixed integer linear programming model easy to solve. And solving the solution by using a mixed integer optimization solver (such as CUROBI), calculating the optimal power flow distribution, and obtaining a final external power supply access scheme for the through bilateral traction power supply system.
Due to the presence of the variable u of 0-1lAnd a continuous variable flThe formula (3) is nonlinear constraint, and the product is converted into a mixed integer linear constraint expression which is easy to solve by adopting a Big-M method:
-ulM1≤fl≤ulM2 (7)
wherein M is1And M2Is a sufficiently large positive number.
Example 2
In the embodiment of the invention, a certain scheme for accessing the external power supply of the electrified railway by adopting a through bilateral traction power supply system is optimized as an example, and the topological structure of the external power supply is shown in fig. 2. The short-circuit capacity of each 220kV substation is 1500 MVA. And single-phase traction transformers are adopted in the 9 traction substations. Sigma1、σ2And σ3Assigned values of 0.4, 0.3, respectively. The average load data of 9 traction substations penetrating through the bilateral traction power supply system is obtained by respectively simulating by using a professional traction load simulation platform (such as OpenPowerNet, ELBAS/WEBANET and the like), and is shown in Table 1.
TABLE 1 average load of traction substation (bilateral supply)
Traction substation Average load/MVA Traction substation Average load/MVA
ZBQ 63.2225 SQQ 64.4
GJQ 85.4975 BDQ 95.87
KDQ 45.43 XLQ 37.34
CYQ 41.305 LLQ 45.02
CDQ 56.88
And (3) substituting the load data in the table 1 into an optimization model to obtain an external power access scheme of the through bilateral traction power supply system shown in fig. 3, wherein S1-S5 are serial numbers of a planned newly-built 220kV power supply point, and LLQ ZBQ are names of 9 newly-built traction substations. The mileage of the transmission line is shown in table 2, the total mileage is 812 kilometers, and a 220kV transformer substation is matched with 16 intervals. According to the measurement and calculation, the total investment of the external power transmission line is about 100 million yuan. It should be noted that in order to satisfy the traction network crossing current constraint, 2 electrical phases must be provided for the full line.
TABLE 2 traction substation access scheme (bilateral supply)
Figure GDA0003632163930000101
The installation capacity results of the three-phase voltage unbalance treatment device of the traction substation are shown in table 3, and the installation capacity of the full-line three-phase voltage unbalance compensation device is 185.06 MVA. According to the survey, the current converter manufacturing cost is 500 yuan/kVA, and the initial investment cost is 0.9253 yuan.
TABLE 3 traction substation three-phase voltage unbalance and management device installation capacity (bilateral supply)
Figure GDA0003632163930000102
Figure GDA0003632163930000111
When single-side power supply is adopted, average load data of 9 traction substations are shown in table 4.
TABLE 4 average load of traction substation (single side power supply)
Traction substation Average load/MVA Traction substation Average load/MVA
ZBQ 86.05 SQQ 106.85
GJQ 124.60 BDQ 80.44
KDQ 46.59 XLQ 39.62
CYQ 38.14 LLQ 59.04
CDQ 90.75
Under the condition of unilateral power supply, although no traction network passes through current constraint, the influence of a traction power supply system structure is limited, and the number of full-line power split phases still reaches 9. Load data in the table 4 are brought into an optimization model, power required by a locomotive is only supplied by a single traction substation due to the adoption of unilateral power supply, and when a grid structure of a bilateral power supply traction power supply system is adopted, the tail end voltage of a traction network is difficult to meet constraint conditions, so that two 220kV substations S2-1 and S2-2 need to be newly built at the power grid side, and an external power supply access scheme of the unilateral traction power supply system shown in the figure 4 is obtained, wherein S1-S5 are planned newly built 220kV power supply point numbers, and LLQ-ZBQ are names of 9 newly built traction substations. The mileage of the transmission line is shown in table 5, the total construction mileage of the transmission line is 1161 km, two 220kV transformer substations are newly built, and the 220kV transformer substations are matched with 16 intervals. According to the measurement and calculation, the total investment of the external power transmission line is about 120 billion yuan.
TABLE 5 traction substation access scheme (unilateral supply)
Figure GDA0003632163930000112
Figure GDA0003632163930000121
The installation capacity results of the three-phase voltage unbalance treatment device of the traction substation are shown in table 6, and the installation capacity of the full-line three-phase voltage unbalance compensation device is 86.34 MVA. The current converter cost obtained by investigation is 500 yuan/kVA, and the initial investment cost is 0.431 yuan.
TABLE 6 unbalance of three-phase voltage of traction substation and installation capacity of treatment device (unilateral power supply)
Figure GDA0003632163930000122
Through comprehensive comparison and selection, compared with a single-side traction power supply system, the long and large ramp section with a weak external power supply has the advantages that the external power supply investment cost can be effectively reduced and the electric split-phase quantity can be greatly reduced by penetrating through the double-side traction power supply system.

Claims (9)

1. A design method for an external power supply access scheme of a through bilateral traction power supply system is characterized by comprising the following steps:
s1, acquiring load process data of the through bilateral traction power supply system, and acquiring a position information set input into a traction substation and an external power supply node position information set;
s2, establishing a target function of the external power supply planning optimization model of the run-through bilateral traction power supply system according to the load process data of the run-through bilateral traction power supply system, the position information collection of the input traction substation and the position information collection of the external power supply node, wherein the target function is as follows: the sum of the investment cost of the transmission network line, the investment of the three-phase voltage unbalance treatment project and the expected running loss value of the through bilateral traction power supply system is minimized;
establishing a constraint condition of an optimization model according to the load process data of the run-through bilateral traction power supply system and the three-phase voltage unbalance limit value;
s3, solving the objective function and the constraint condition to obtain an optimized external power access scheme of the through bilateral traction power supply system;
the objective function is defined as the function of the target,
Figure FDA0003632163920000011
the subscript l represents the line number of an external power supply, g represents the number of a three-phase voltage unbalance treatment device of the traction substation, tt represents the number of a traction transformer of the traction substation, q represents the number of a traction network between two adjacent traction substations, and omegaLRepresents the newly-built line collection of the external power supply omegaGDevice for treating three-phase voltage unbalance of representative traction substationTRepresents a traction transformer collection of a traction substation, omegaQNRepresenting a traction network collection between two adjacent traction substations; c. ClFor the investment cost of newly-built line l, ulPut a decision variable, u, for line ll1 is the investment to construct the line l, ul0 is a non-investment linegInvestment cost v of three-phase voltage unbalance treatment device g for newly-built traction substationgFor the decision variables v of the three-phase voltage unbalance control device ggThree-phase voltage unbalance treatment device g, v for investment constructiong0 is a three-phase power without investmentA pressure unbalance treatment device g is arranged on the device,
Figure FDA0003632163920000021
in order to achieve active power loss during the operation of the line l,
Figure FDA0003632163920000022
the active power loss when a single-phase traction transformer tt of a traction substation operates,
Figure FDA0003632163920000023
in order to provide active power loss during operation of the traction network q,
Figure FDA0003632163920000024
representing expected value of running loss, sigma, of through bilateral traction power supply system1、σ2And σ3The weight coefficients are respectively the investment cost of the transmission network line, the investment of the three-phase voltage unbalance treatment project and the expected value of the running loss of the run-through bilateral traction power supply system.
2. The design method of the external power access scheme of the through bilateral traction power supply system according to claim 1, wherein the constraint condition includes: the method comprises the steps of node active power balance constraint, transmission capacity constraint of a transmission line, traction network through current constraint, traction substation three-phase voltage unbalance constraint and contact network working voltage fluctuation constraint.
3. The design method of the external power supply access scheme of the through bilateral traction power supply system according to claim 2, wherein the formula of the active power balance constraint of the node is,
Figure FDA0003632163920000025
wherein p istsLoad active power, p, of traction substation ts for connection to external power i nodedFor external power supplyActive power, omega, of other loads d on node iTS,iRepresenting a set of traction substations, Ω, located at the i-node of an external power supplyD,iRepresenting other sets of loads, Ω, at the external supply i-nodeL,iRepresents a power transmission line collection omega with a node i as a head end and a node j as a tail endL,jRepresenting a power transmission line set, p, with node j as the head end and node i as the tail endl,ijAnd pl,jiFor the active power transmitted on the transmission line l, the external power supply nodes at the head end and the tail end are respectively a node i and a node j, ij represents the node from the external power supply node i at the head end to the external power supply node j at the tail end, and ji represents the node from the external power supply node j at the tail end to the external power supply node i at the head end.
4. The design method of the external power access scheme of the through bilateral traction power supply system according to claim 2, wherein the transmission capacity constraint of the transmission line is formulated as,
Figure FDA0003632163920000031
wherein f islFor transmission capacity of transmission line, -fl min、fl maxRespectively the lower limit and the upper limit of the power flow of the transmission line l, ulPut a decision variable, Ω, for line lLAnd a new line set represents the external power supply, and the subscript l represents the line number of the external power supply.
5. The design method of the external power access scheme of the through bilateral traction power supply system according to claim 4, wherein the transmission capacity constraint of the transmission line is converted into a mixed integer linear constraint expression which is easy to solve by a Big-M method:
-ulM1≤fl≤ulM2
wherein M is1And M2Is a positive number of ulAnd (5) putting decision variables for the line l.
6. The design method of the external power supply access scheme of the through bilateral traction power supply system according to claim 2, wherein the traction network through current constraint is formulated as,
Figure FDA0003632163920000032
where the indices x and x 'each denote a certain phase of the phase sequence a, b, c, x ≠ x',
Figure FDA0003632163920000033
and
Figure FDA0003632163920000034
respectively the actual through current and the through current allowable value flowing through the traction network,
Figure FDA0003632163920000035
and
Figure FDA0003632163920000036
respectively representing two-phase current flowing into the single-phase traction transformer tt, epsilon being the ratio of the voltage at the high-voltage side of the single-phase traction transformer tt to the traction voltage, Zs,iEquivalent impedance, Z, at external supply node i for access to traction substation tsttImpedance, Z, of single-phase traction transformer tt of traction transformerqTo the impedance of the traction network, Zl,tsiTo connect the line impedance between the traction substation ts and the external power supply node i.
7. The design method of the external power supply access scheme of the through bilateral traction power supply system according to claim 2, wherein the constraint of the three-phase voltage unbalance of the traction substation is expressed by a formula,
Figure FDA0003632163920000041
wherein the content of the first and second substances,
Figure FDA0003632163920000042
for negative-sequence currents, VUF, generated by traction substations ts*For three-phase voltage unbalance limits, UqFor drawing net pressure, SdcAnd epsilon is the ratio of the voltage of the high-voltage side of the single-phase traction transformer tt to the traction measurement voltage, which is the short-circuit capacity of the traction transformer.
8. The design method of the external power supply access scheme of the through bilateral traction power supply system according to claim 2, wherein the constraint of the fluctuation of the working voltage of the overhead line system is expressed by a formula,
Figure FDA0003632163920000043
wherein the content of the first and second substances,
Figure FDA0003632163920000044
and
Figure FDA0003632163920000045
respectively the lowest voltage and the highest voltage allowed by a contact net when the traction power supply system operates normally, UqIs the working voltage of the contact net.
9. The design system of the external power supply access scheme of the through bilateral traction power supply system is characterized by comprising at least one processor and a memory which is in communication connection with the at least one processor; the memory stores instructions executable by the at least one processor to enable the at least one processor to perform the method of any one of claims 1 to 8.
CN201911348665.0A 2019-12-24 2019-12-24 Design method for external power supply access scheme of through bilateral traction power supply system Active CN110979105B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911348665.0A CN110979105B (en) 2019-12-24 2019-12-24 Design method for external power supply access scheme of through bilateral traction power supply system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911348665.0A CN110979105B (en) 2019-12-24 2019-12-24 Design method for external power supply access scheme of through bilateral traction power supply system

Publications (2)

Publication Number Publication Date
CN110979105A CN110979105A (en) 2020-04-10
CN110979105B true CN110979105B (en) 2022-06-14

Family

ID=70074860

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911348665.0A Active CN110979105B (en) 2019-12-24 2019-12-24 Design method for external power supply access scheme of through bilateral traction power supply system

Country Status (1)

Country Link
CN (1) CN110979105B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113076660B (en) * 2021-04-28 2023-01-31 中铁二院工程集团有限责任公司 Electrified railway circulation calculation method adopting hybrid power supply system bilateral power supply mode
CN113258579B (en) * 2021-06-28 2023-01-31 中铁二院工程集团有限责任公司 Method for calculating short-circuit current of electrified railway of hybrid power supply mode bilateral power supply system
CN114336641B (en) * 2022-03-17 2022-05-24 西南交通大学 Three-phase power supply ride-through power utilization system and control method

Citations (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08310279A (en) * 1995-05-18 1996-11-26 Nissin Electric Co Ltd Reactive power compensating device
JP2000069763A (en) * 1998-08-24 2000-03-03 Nissin Electric Co Ltd Power supply device for electric railway
JP2007215314A (en) * 2006-02-09 2007-08-23 Tokyo Electric Power Co Inc:The Support system for determining condition when connecting distributed power supply to power distribution network and its program
CN103368173A (en) * 2013-05-21 2013-10-23 南方电网科学研究院有限责任公司 Active power flow optimizing distribution method for alternating-direct current parallel system containing soft direct current power transmission
CN103490410A (en) * 2013-08-30 2014-01-01 江苏省电力设计院 Micro-grid planning and capacity allocation method based on multi-objective optimization
CN203592908U (en) * 2013-11-18 2014-05-14 中铁第一勘察设计院集团有限公司 Direct current-alternating current traction power supply system
US8772954B1 (en) * 2013-04-15 2014-07-08 Caterpillar Inc. Power balancing for a dual generator single DC link configuration for electric drive propulsion system
EP2942855A1 (en) * 2014-05-08 2015-11-11 Rheinisch-Westfälisch-Technische Hochschule Aachen Method and system for monitoring distribution systems
CN105071377A (en) * 2015-07-17 2015-11-18 华中科技大学 Power island
CN105790274A (en) * 2016-03-09 2016-07-20 西南交通大学 Power flow control device and control method for run-through power supply system converter type traction substation
CN106410817A (en) * 2016-09-29 2017-02-15 湘潭大学 Negative sequence, reactive power and voltage fluctuation comprehensive optimization compensation method for tractive power supply system
CN106505593A (en) * 2016-10-14 2017-03-15 国网信通亿力科技有限责任公司 A kind of method of the analysis of distribution transforming three-phase imbalance and load adjustment based on big data
CN107404115A (en) * 2017-09-05 2017-11-28 山东鼎维数字技术有限公司 A kind of remote distributed DC power-supply system and its control method
CN108767891A (en) * 2018-03-15 2018-11-06 国网浙江象山县供电有限公司 Feeder line photovoltaic is pressed to dissolve model in medium voltage distribution network single
CN109435783A (en) * 2018-10-25 2019-03-08 中铁二院工程集团有限责任公司 Negative sequence management system for electric railway traction power supply system AT power supply mode
CN109659980A (en) * 2019-01-22 2019-04-19 西南交通大学 The tractive power supply system energy management optimization method of integrated hybrid energy-storing and photovoltaic devices
CN109687484A (en) * 2019-01-22 2019-04-26 西南交通大学 A kind of electric railway external electrical network access scheme optimum design method
CN110103779A (en) * 2019-05-13 2019-08-09 西南交通大学 A kind of Design for Traction Substation method of cable perforation ac power supply system
CN110247365A (en) * 2019-06-20 2019-09-17 西南交通大学 A kind of electric railway perforation power supply system and its fault section recognition methods
CN110365039A (en) * 2018-03-26 2019-10-22 北京天诚同创电气有限公司 Control method, control device and the microgrid inverter of microgrid inverter

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2505386A (en) * 2011-06-13 2014-02-26 Gridpoint Inc Valuating energy management systems
US8977524B2 (en) * 2012-03-06 2015-03-10 Siemens Aktiengesellschaft Interior point method for reformulated optimal power flow model
EP2831972B1 (en) * 2012-03-30 2016-02-03 Sony Corporation Energy storage
EP2806520A1 (en) * 2013-05-22 2014-11-26 Vito NV Power supply network control system and method
US10218179B2 (en) * 2014-03-07 2019-02-26 The Regents Of The University Of California Method and system for dynamic intelligent load balancing
CN104210385B (en) * 2014-08-19 2016-09-07 吉林大学 The omnidistance electric railway network system without negative phase-sequence interval unpowered net
CN107104443B (en) * 2017-06-21 2023-05-23 西南交通大学 Power electronic transformer

Patent Citations (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08310279A (en) * 1995-05-18 1996-11-26 Nissin Electric Co Ltd Reactive power compensating device
JP2000069763A (en) * 1998-08-24 2000-03-03 Nissin Electric Co Ltd Power supply device for electric railway
JP2007215314A (en) * 2006-02-09 2007-08-23 Tokyo Electric Power Co Inc:The Support system for determining condition when connecting distributed power supply to power distribution network and its program
US8772954B1 (en) * 2013-04-15 2014-07-08 Caterpillar Inc. Power balancing for a dual generator single DC link configuration for electric drive propulsion system
CN103368173A (en) * 2013-05-21 2013-10-23 南方电网科学研究院有限责任公司 Active power flow optimizing distribution method for alternating-direct current parallel system containing soft direct current power transmission
CN103490410A (en) * 2013-08-30 2014-01-01 江苏省电力设计院 Micro-grid planning and capacity allocation method based on multi-objective optimization
CN203592908U (en) * 2013-11-18 2014-05-14 中铁第一勘察设计院集团有限公司 Direct current-alternating current traction power supply system
EP2942855A1 (en) * 2014-05-08 2015-11-11 Rheinisch-Westfälisch-Technische Hochschule Aachen Method and system for monitoring distribution systems
CN105071377A (en) * 2015-07-17 2015-11-18 华中科技大学 Power island
CN105790274A (en) * 2016-03-09 2016-07-20 西南交通大学 Power flow control device and control method for run-through power supply system converter type traction substation
CN106410817A (en) * 2016-09-29 2017-02-15 湘潭大学 Negative sequence, reactive power and voltage fluctuation comprehensive optimization compensation method for tractive power supply system
CN106505593A (en) * 2016-10-14 2017-03-15 国网信通亿力科技有限责任公司 A kind of method of the analysis of distribution transforming three-phase imbalance and load adjustment based on big data
CN107404115A (en) * 2017-09-05 2017-11-28 山东鼎维数字技术有限公司 A kind of remote distributed DC power-supply system and its control method
CN108767891A (en) * 2018-03-15 2018-11-06 国网浙江象山县供电有限公司 Feeder line photovoltaic is pressed to dissolve model in medium voltage distribution network single
CN110365039A (en) * 2018-03-26 2019-10-22 北京天诚同创电气有限公司 Control method, control device and the microgrid inverter of microgrid inverter
CN109435783A (en) * 2018-10-25 2019-03-08 中铁二院工程集团有限责任公司 Negative sequence management system for electric railway traction power supply system AT power supply mode
CN109659980A (en) * 2019-01-22 2019-04-19 西南交通大学 The tractive power supply system energy management optimization method of integrated hybrid energy-storing and photovoltaic devices
CN109687484A (en) * 2019-01-22 2019-04-26 西南交通大学 A kind of electric railway external electrical network access scheme optimum design method
CN110103779A (en) * 2019-05-13 2019-08-09 西南交通大学 A kind of Design for Traction Substation method of cable perforation ac power supply system
CN110247365A (en) * 2019-06-20 2019-09-17 西南交通大学 A kind of electric railway perforation power supply system and its fault section recognition methods

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
基于LCC的外部电源薄弱地区同相贯通牵引供电方案优化;陈民武等;《中国铁道科学》;20190515(第03期);104-111页 *
电气化铁路牵引变电所位置及安装容量优化设计;陈宏伟等;《电力系统及其自动化学报》;20161115(第11期);104-110页 *
贯通式同相供电方案优化设计;蒋俊等;《电气化铁道》;20171015(第05期);31-34页 *
高速铁路牵引变压器容量与配置方案优化研究;陈民武等;《中国铁道科学》;20130915(第05期);70-75页 *

Also Published As

Publication number Publication date
CN110979105A (en) 2020-04-10

Similar Documents

Publication Publication Date Title
CN110979105B (en) Design method for external power supply access scheme of through bilateral traction power supply system
He et al. Harmonic resonance assessment to traction power-supply system considering train model in China high-speed railway
CN101752870B (en) Method for analysis of available power supply capacity of medium voltage distribution network
CN103839116B (en) A kind of substation capacity collocation method based on different power supply areas
Chen Criteria to estimate the voltage unbalances due to high-speed railway demands
CN202026095U (en) Digital-analog mixing emulational test platform used for high voltage direct current transmission engineering
CN103236023B (en) A kind of acquisition methods of the AC-HVDC scope of application
Pilo et al. A simulation tool for the design of the electrical supply system of high-speed railway lines
Cui et al. High‐frequency resonance suppression of high‐speed railways in China
CN107176063B (en) Power supply structure of external power grid of electrified railway
CN106033894A (en) Method for judging stability of extra-high-voltage direct-current multi-drop-point grid
Bader et al. Adaptation of a traction DC power system for high-speed traffic
CN106651168A (en) Method and device for evaluating influence of electrified railway on power grid
CN210224973U (en) Integrated compensation device for in-phase power supply of electrified railway
CN116054126A (en) Equivalent method of electrified railway through power supply system
Chen et al. Systematized short-circuit analysis of a 2× 25 kV electric traction network
CN109359344B (en) Modeling method considering mixed running influence of ordinary iron and high-speed rail passenger and goods
Kilter et al. Modelling of high-speed electrical railway system for transmission network voltage quality analysis: Rail Baltic case study
Hosseini et al. Power quality improvement of DC electrified railway distribution systems using hybrid filters
Panda et al. Cost‐effective upgrade of the Dutch traction power network: Moving to Bi‐directional and controllable 3 kV DC substations for improved performance
Kilter et al. Assessment of transmission network voltage unbalance in connection of high-speed electrical railway connection
CN206807025U (en) A kind of Modularized parallel redundant railway power line cleaner
Cherepanov et al. Modeling of traction power supply systems for movement of high-speed trains
Battistelli et al. Short circuit modelling and simulation of 2× 25 kV high speed railways
Serrano-Jimenez et al. Modeling, Simulation and Analysis of an Advanced Mono-Voltage DC Converter-Based Electrical Railway Power Supply System for High Speed Lines

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant