CN102868227B - Medium voltage distribution-network looped-network switching operation method - Google Patents

Medium voltage distribution-network looped-network switching operation method Download PDF

Info

Publication number
CN102868227B
CN102868227B CN201210374142.5A CN201210374142A CN102868227B CN 102868227 B CN102868227 B CN 102868227B CN 201210374142 A CN201210374142 A CN 201210374142A CN 102868227 B CN102868227 B CN 102868227B
Authority
CN
China
Prior art keywords
network
looped
equipment
looped network
voltage distribution
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210374142.5A
Other languages
Chinese (zh)
Other versions
CN102868227A (en
Inventor
郭雪丽
杜九菊
齐昌宵
马涛
李新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Nanyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Nanyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Nanyang Power Supply Co of State Grid Henan Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201210374142.5A priority Critical patent/CN102868227B/en
Publication of CN102868227A publication Critical patent/CN102868227A/en
Application granted granted Critical
Publication of CN102868227B publication Critical patent/CN102868227B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a medium voltage distribution-network looped-network switching operation method. Loop closing load flow calculation, short circuit calculation analysis and the existing site checking phase sequence are carried out before looped-network switching, a non-out-of-limit protection constant value and equipment dynamic and static limits are guaranteed, line phase sequences of looped-network operation is guaranteed, loop closing time is controlled to be minimum, the shorter the loop closing time is, the better the effects are, unforeseen circumstances such as line overload, relaying protection movement tripping, short circuits of closing loop moment power grids, damage to safety of lines and equipment and even equipment damage caused by big circulation are effectively avoided, safe operation of the power grid is guaranteed, operating efficiency of the power distribution network is effectively improved, and adverse effects of construction and overhaul on power supply management and users are effectively avoided.

Description

Middle voltage distribution networks looped network grid switching operation method
Technical field
The present invention relates to electric power overhaul technology field, particularly relate to a kind of middle voltage distribution networks looped network grid switching operation method.
Background technology
Urban Medium Voltage Distribution Network directly towards numerous urban subscribers, along with the development in city, construction, maintenance more and more frequent.Traditional construction method, before and after maintenance, all needs to carry out power failure grid switching operation, and each operation power failure 20-30 minute, causes frequent power failure thus, cause inconvenience and huge economic loss to power supply management and user.
Summary of the invention
The object of the invention is to overcome prior art deficiency, provide a kind of power failure can carry out the middle voltage distribution networks looped network grid switching operation method of grid maintenance construction.
The technical scheme adopted for realizing object of the present invention is: a kind of middle voltage distribution networks looped network grid switching operation method, comprises the following steps:
A. carry out closed loop power flow to calculate and short circuit calculation analysis, move the steady limit for criterion with not out-of-limit protection definite value and equipment, auxiliary dispatching decision-making;
B. on-the-spot Check Phase Sequence, guarantees that the line phase-sequence detection that looped network operates is consistent;
C. first interconnection switch between transformer station is closed;
D. the block switch of faulty line near described interconnection switch end is separated again;
E. the block switch of faulty line near transformer substation end is finally separated.
The present invention adopts the method for looped network grid switching operation, closed loop power flow calculating should be carried out before looped network back brake, short circuit calculation is analyzed and present on-the-spot Check Phase Sequence, guarantee that not out-of-limit protection definite value and equipment move the steady limit, guarantee that the line phase-sequence detection that looped network operates is consistent, and by cyclization time controling to minimum, the smaller the better, efficiently avoid the circulation that generation is larger, cause circuit overload, relaying protection action is tripped, and cyclization moment electrical network is short-circuited, jeopardize the safety of circuit and equipment, even make the generation of the fortuitous events such as device damage, ensure that the safe operation of electrical network, effectively improve the operational efficiency of power distribution network, efficiently avoid construction, maintenance is to the adverse effect of giving power supply management and user.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, the present invention is described further:
Fig. 1 is three segmentation two interconnector figure of the present invention;
Fig. 2 is that cyclization of the present invention simplifies procedure chart;
Fig. 3 is nodal equilibrium equation evolution diagram;
Contrast table before and after the cyclization of Fig. 4 short circuit current.
Embodiment
Embodiment one
Tidal current computing method and software for calculation
Load flow calculation mathematically can be summed up as and solves Nonlinear System of Equations, and its Mathematical Modeling is write a Chinese character in simplified form as follows:
F (X)=0 is Nonlinear System of Equations
Wherein:
F=(f1, f2 ..., f n) and T is nodal equilibrium equation formula;
X=(x1, x2 ..., x n) and T is each node voltage to be asked.
Software for calculation: " Based on Power System Analysis Software Package " (PSASP) that DianKeYuan development is write can be adopted.
As shown in Figure 2: on the south positive electricity net 110kV build west and become and become cyclization simplify procedure chart into example with 110kV riverfront, build west change before supposing cyclization, riverfront change high side bus voltage 1,2 node is respectively U1, U2, medium voltage side 3,4 node U3, U4, transmission power is respectively Sa, Sb, and the equivalent impedance of node 1,4 relative system is respectively Z1, Z2; Circuit L1, L2 impedance is respectively ZL1, ZL2; Transformer station's other feeder load sum equivalences except cyclization feeder line are a point load, be respectively S1, S2, UN is cyclization point voltage after cyclization, so, as shown in Figure 3: from formula (5) (6), the power flow through in loop can think the superposition of two power, a part be voltage equal time natural equal power, another part power depends on both end voltage phasor difference with looped network total impedance , for circulating power, , circulating power is directly proportional to both end voltage difference, is inversely proportional to loop total impedance.When cyclization point both end voltage is equal, =0, larger, circulating power is larger, and loop total impedance is less, and circulating power is larger.
So looped network grid switching operation reduces the measure of circulation: by measures such as main transformer pressure regulation, cyclization circuit both end voltage difference is adjusted to suitably little, to improve the ratio of distribution line looped network operation.
Embodiment two
Short circuit calculation
With the not super switch rupturing capacity of the most serious three short circuit current for criterion, when exceeding, abandon looped network operation.Main calculating cyclization moment:
(1) cyclization circuit generation three-phase shortcircuit;
(2) 10kV bus generation three-phase shortcircuit;
(3) 110 kV bus generation three-phase shortcircuits;
(4) 220 kV bus generation three-phase shortcircuits.
If above-mentioned four kinds of situation short circuit currents are all no more than each electric pressure switch rupturing capacity, then during cyclization pair
Switch at different levels is without impact.
As shown in Figure 4: 10kV west supplies two wires cyclization moment for two wires and 10kV shore, calculation of short-circuit current table, as can be seen from the table, distribution line cyclization moment, after cyclization, short circuit current all increases to some extent than short circuit current before cyclization, but to 220kV, 110kV electric network influencing is very little, almost negligible, 110 kV Luo Zhuan become, after jujube woods becomes main transformer fanout operation, short circuit current reduces greatly, but after 220 kV transforming plant main transformer split operations, short circuit current reduces very little, think the ratio improving distribution line looped network grid switching operation, 110kV transforming plant main transformer normal operating mode should be fanout operation, and 110kV transformer station is all configured with mother automatic throw-in equipment of emergency power supply, power supply reliability still can ensure, system short circuit capacity can also be reduced, be conducive to the safe operation of electrical network and the safe looped network grid switching operation of distribution.
Embodiment three
As shown in Figure 1, a kind of middle voltage distribution networks looped network grid switching operation method, comprises the following steps:
F. carry out closed loop power flow to calculate and short circuit calculation analysis, move the steady limit for criterion with not out-of-limit protection definite value and equipment, auxiliary dispatching decision-making;
G. on-the-spot Check Phase Sequence, guarantees that the line phase-sequence detection that looped network operates is consistent;
H. first interconnection switch L1 between transformer station A, B is closed;
I. the block switch K1 that faulty line A holds near described interconnection switch L1 is separated again;
J. the block switch Z1 that faulty line A holds near transformer station A is finally separated.
The present invention adopts the method for looped network grid switching operation, closed loop power flow calculating should be carried out before looped network back brake, short circuit calculation is analyzed and present on-the-spot Check Phase Sequence, guarantee that not out-of-limit protection definite value and equipment move the steady limit, guarantee that the line phase-sequence detection that looped network operates is consistent, and by cyclization time controling to minimum, the smaller the better, efficiently avoid the circulation that generation is larger, cause circuit overload, relaying protection action is tripped, and cyclization moment electrical network is short-circuited, jeopardize the safety of circuit and equipment, even make the generation of the fortuitous events such as device damage, ensure that the safe operation of electrical network, effectively improve the operational efficiency of power distribution network, efficiently avoid construction, maintenance is to the adverse effect of giving power supply management and user.

Claims (1)

1. a middle voltage distribution networks faulty line looped network grid switching operation method, is characterized in that: comprise the following steps:
A. carry out closed loop power flow to calculate and short circuit calculation analysis, move the steady limit for criterion with not out-of-limit protection definite value and equipment, auxiliary dispatching decision-making;
B. by main transformer adjusting pressure measure, cyclization circuit both end voltage difference is adjusted to suitably little, to improve the ratio of distribution line looped network operation, middle voltage distribution networks transforming plant main transformer normal operating mode is fanout operation, and transformer station is all configured with mother automatic throw-in equipment of emergency power supply;
C. on-the-spot Check Phase Sequence, guarantees that the line phase-sequence detection that looped network operates is consistent;
D. first interconnection switch between transformer station is closed;
E. the block switch of faulty line near interconnection switch end is separated again;
F. the block switch of faulty line near transformer substation end is finally separated.
CN201210374142.5A 2012-10-07 2012-10-07 Medium voltage distribution-network looped-network switching operation method Expired - Fee Related CN102868227B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210374142.5A CN102868227B (en) 2012-10-07 2012-10-07 Medium voltage distribution-network looped-network switching operation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210374142.5A CN102868227B (en) 2012-10-07 2012-10-07 Medium voltage distribution-network looped-network switching operation method

Publications (2)

Publication Number Publication Date
CN102868227A CN102868227A (en) 2013-01-09
CN102868227B true CN102868227B (en) 2015-05-06

Family

ID=47446902

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210374142.5A Expired - Fee Related CN102868227B (en) 2012-10-07 2012-10-07 Medium voltage distribution-network looped-network switching operation method

Country Status (1)

Country Link
CN (1) CN102868227B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103560513A (en) * 2013-11-21 2014-02-05 国家电网公司 Method and device for determining loop closing time
CN105429137B (en) * 2015-12-09 2017-10-17 云南电网有限责任公司红河供电局 The method that distribution network closed loop turns power supply
CN105552882B (en) * 2015-12-09 2018-03-27 云南电网有限责任公司红河供电局 A kind of control method of power network cyclization
CN110865255B (en) * 2019-11-21 2021-10-22 国网北京市电力公司 10kV power distribution network line reversing method
CN112433118B (en) * 2020-11-16 2022-07-01 国网山东省电力公司聊城供电公司 Anti-misoperation simulation device and method for 10kV medium-voltage power generation vehicle

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
中山市配电网合环辅助决策支持系统开发;庞嘉琦;《中国优秀硕士学位论文全文数据库》;20111215;说明书第1页至10页,第23页最后一段至26页,第60页 *

Also Published As

Publication number Publication date
CN102868227A (en) 2013-01-09

Similar Documents

Publication Publication Date Title
Liu Ultra-high voltage AC/DC grids
Samuelsson et al. Active distribution network—Demonstration project ADINE
CN103954874B (en) Whole-network-and-local-model-combined transformer substation running status analyzing method
CN102868227B (en) Medium voltage distribution-network looped-network switching operation method
Weng et al. Distributed processing based fault location, isolation, and service restoration method for active distribution network
El-Helw et al. Evaluation of the suitability of a fixed speed wind turbine for large scale wind farms considering the new UK grid code
CN104767195A (en) Small reactance value choose method during ultrahigh voltage autotransformer neutral point grounding in small reactance mode
Seo New adaptive reclosing technique using second-order difference of THD in distribution system with BESS used as uninterruptible power supply
Wang et al. Adaptive single-phase/three-phase reclosing scheme for transmission lines in passive network supplied by MMC-HVDC
Zheng et al. Fault identification scheme for UPFC compensated transmission line based on characteristic voltage active injection
Laaksonen et al. New functionalities and features of ieds to realize active control and protection of smart grids
Robak et al. Transient stability enhancement by series braking resistor control using local measurements
Rong et al. Methods for transient AC overvoltage reduction at wind farm terminal
Zhi-hui et al. Modeling and simulation research of large-scale AC/DC hybrid power grid based on ADPSS
Nilsson et al. Application examples of the thyristor controlled series capacitor
Wang et al. Research on overvoltage and fault of a UHV AC/DC hybrid system
Khan et al. Transient stability enhancement of power system using UPFC (unified power flow controller)
Cao et al. An improved fault recovery strategy for active distribution network considering LVRT capability of DG
Pessanha et al. Power system stability reinforcement based on network expansion: a practical case
An et al. Application of wide area monitoring protection and control in an electricity distribution network
Dong et al. The offline accident of the large-scale wind generator system and its protection & control scheme
Kudiyarasan et al. Modern analysis of power flow and network stability of transmission lines for nuclear power dispatch
CN205039532U (en) Relay protection disposes device based on little electric access system
Wu et al. Research on the influence of Multi-HVDC power coordinated control strategy on frequency stability in multi partitioned power grid
Fischer et al. Case study of a multi-infeed HVDC system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE GRID CORPORATION OF CHINA

Free format text: FORMER OWNER: HENAN ELECTRIC POWER COMPANY NANYANG POWER SUPPLY BRANCH

Effective date: 20150401

Owner name: NANYANG POWER SUPPLY COMPANY, STATE GRID HENAN ELE

Effective date: 20150401

COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 473000 NANYANG, HENAN PROVINCE TO: 100000 XICHENG, BEIJING

TA01 Transfer of patent application right

Effective date of registration: 20150401

Address after: 100000 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant after: State Grid Corporation of China

Applicant after: Nanyang Power Supply Company, State Grid Henan Electric Power Company

Address before: 473000 Henan City, Nanyang province people's North Road, No. 268

Applicant before: Henan Electric Power Company Nanyang Power Supply Branch

C14 Grant of patent or utility model
GR01 Patent grant